Case Study, General Contracting

Interior framing is just about complete.

Electrical and mechanical rough-in continues.

Stone veneer is nearing completion on the main building, and weather permitting, next week the vinyl siding will be installed above the stone areas.

Curb and sidewalk areas have been excavated.  Good weather will bring concrete progress in the Read More

Case Study, Food Processing

We’ve been working on a project for some time now for a long-time customer.  This entails constructing an insulated chemical room inside their existing food processing facility.

Initially, we demolished portions of the floor slab to reinforce and pour a new slab to bear the weight of their chemical tanks Read More

Case Study, General Contracting

The concrete floor slab is now poured.

Rough-in of electrical/mechanical continues, and interior wall framing has started.

Many exterior finishes are either completed, or well under way.

  There are more than (70) windows and sets of shutters on this building.

The stone veneer is progressing nicely.  The next few weeks Read More

Case Study, General Contracting

Finally, a few days of good weather in a row to make some progress.  Exterior walls are complete and ready for roof trusses at CSCD.

Trusses have been delivered, and are ready for erection.  More wind and rain in the forecast, which has been the norm this winter.. Read More